Only 17% of Amrit 2.0 Green Park in Shahdol Completed After Two Years, Authorities Move to Blacklist Contractor
📷 Image: Wikimedia Commons / कृष्ण कान्त शर्मा
Sarkari Yojana

Only 17% of Amrit 2.0 Green Park in Shahdol Completed After Two Years, Authorities Move to Blacklist Contractor

✍️ Amar Ujala · Madhya Pradesh 🗓 26 Nov 2026, 12:16 PM 👁 20
Share: 💬 WhatsApp 📘 Facebook 𝕏 Post

Construction of the Amrit 2.0 park near Ponang Talab in Shahdol has stalled, with just 17% of work finished in over two years, prompting the Chief Minister’s Office to consider blacklisting the contractor.

The Amrit 2.0 scheme envisions a series of green‑space parks across Madhya Pradesh, and the Shahdol project near Ponang Talab was slated for completion within a year. Work began more than two years ago, but recent inspections reveal that only about 17 per cent of the planned landscaping, pathways and recreational facilities have been installed.

Repeated notices were issued to the contracted construction firm after progress remained negligible despite multiple deadlines. Site officials reported that essential earth‑moving and planting activities were either delayed or abandoned, leading to mounting public criticism.

In response, the Chief Minister’s Office (CMO) has directed senior officials to draft a proposal for blacklisting the contractor. The move aims to recover the delayed timeline, enforce contractual penalties and possibly re‑tender the remaining work to a more reliable firm.

If the blacklisting proceeds, the project could see a change in management, which may accelerate completion but could also entail additional costs and a revised schedule for the community that has been awaiting the park’s opening.