Construction of a four-lane bridge over the Chambal River in Madhya Pradesh is progressing rapidly. Fifteen out of thirty planned pillars have been erected in just six months.

The Madhya Pradesh Road Development Corporation (MPRDC) initiated the construction project in April. The ambitious project, estimated to cost ₹35 crore, aims to connect vital regions across the Chambal River. The construction team has achieved significant progress in a short timeframe, with fifteen pillars already standing tall. The remaining work is expected to be completed by March 2024.